Manta Bay Construction Update Q2, 2025
Phase 1- Enabling Package (G5% was done)
- The Project site mobilization was completed.
- The Soil Investigations were done.
- Soil Improvement was completed.
- The shoring system was done.
- The Dewatering work was done.
- The Excavation works were done.
- The Piling work was done successfully.
- All tests were done.
Final formation leveling in progressThe expected date of completion for the full package of enabling work is 30th May 2025.
Phase 2- Main Package- Main Contractor (In Progress)
- Main Contractor (NSE) was appointed successfully.
- The site mobilization on the site is in progress.